The project’s termination also stems from the “lack of a committed partner,” as NASA put it, presumably referring to Maxar, a key contractor for OSAM-1. A report from NASA’s inspector general in October highlighted Maxar’s “poor performance,” citing the company’s underestimation of the project’s scope and complexity, a lack of full understanding of NASA’s technical requirements, and deficiencies in necessary expertise. The company was already taking a financial loss on its OSAM-1 involvement. The nature of Maxar’s fixed-price contract with NASA, which didn’t “provide NASA adequate flexibility to incentivize Maxar to improve its performance,” contributed to staffing challenges and project delays, according to the OIG.